April 23, 2026
The delivery and installation phase for key components of the Electric Energy Storage Facility has begun in Żarnowiec. The first units of the DC-Link containerized energy storage system are arriving at the project site and are being immediately installed
at their designated locations – on specially prepared foundation slabs. All units were manufactured in Poland.